Silvercorp Adds $14.6 Million To El Domo Budget, Now $298.2 Million, And Pushes Production To November 2027
Diesel costs, rain-driven water works and a four-month weather delay reshape the build plan for the Ecuador project.
Silvercorp Metals, a Canadian miner of silver, gold, lead and zinc, raised the construction budget for its El Domo project in Ecuador to $298.2 million, up $14.6 million from a February 4, 2026 estimate of $283.6 million, the company said Tuesday. It also now forecasts production by November 1, 2027, a four-month slip it blames on extended rainfall caused by Super El Nino.
Diesel is the biggest add
The 2021 Feasibility Study budget for El Domo was $248 million, the company noted. Ecuador ended diesel subsidies, and the price rose from under $3 a gallon in December 2024 to $5.64 in October 2026, an increase of $2.70 a gallon. That adds $8.3 million for the remaining work: $3.6 million for the site-preparation package and $4.7 million for open-pit mining and stripping.
Heavy rain added $4.7 million more: $3.5 million to upgrade and reinforce water-management designs, plus $1.2 million for site cleaning. Two cofferdams, drainage pipes under the tailings storage facility starter dam and cemented roadside ditches add close to $2 million.
Power and the plant account for most of the rest. Site power equipment rises $2.4 million on detailed engineering, two new reactive power compensators cost $2 million plus $1.3 million of related items, and the processing plant adds $3.7 million based on actual quantities in its construction contract.
$9.8 million in offsetting savings
Savings of $9.8 million trimmed the increase. Cutting contingency saves $2.7 million, using rock from plant-site preparation for haul roads saves $1.8 million, and dropping the West Non-contact Water Channel saves $1.5 million because the explosives magazine site has effectively diverted surface water. A smaller permanent camp saves $0.7 million, since the current construction camp is satisfactory for long-term use.
Spending so far and the powerline
Actual spending through September 30, 2026 totaled $84.6 million, leaving $213.6 million to spend. Much of the plant's cost is prefabricated steel that has been ordered and shipped, with payment pending arrival at the Ecuador port and installation. Most equipment has been ordered with a down payment of about 30%, roughly $10.6 million.
The external powerline has been continuously delayed because CNEL has required more reviews and approvals; only a substation at the site has started construction. Ten generator sets of 17 MW capacity are built and ready to ship as an independent power supply.
The plant site is protected by the Northeast Non-contact Water Channel, and foundations are well advanced, including 92% complete for the fine ore bin and 86% for the dewatering plant.
Silvercorp's updated schedule has El Domo in production by November 1, 2027, with the powerline still waiting on CNEL approvals.