Silvercorp's Ying District Silver Output Fell 41% In Second Quarter; Company Revenue Down 13% To $72.1 Million
Production at Ying resumed and ended the quarter at a 90% operating rate, and full financial results are due November 5 after the close.
Silvercorp Metals reported second-quarter revenue of $72.1 million, down 13% from the same quarter a year earlier, in an operations update released Monday and furnished to the SEC on Form 6-K. The company attributed the decline to lower production, partly offset by higher metal prices.
What the release says
At the Ying Mining District in China, silver output fell 41% from the second quarter of fiscal 2026 to 0.9 million ounces. Silver equivalent fell 42% to 1.0 million ounces, and gold fell 34% to 1,371 ounces. Ying lead fell 41% to 7.6 million pounds and zinc fell 51% to 0.7 million pounds. The company said this matched the 40-50% impact it disclosed on June 29, 2026.
Ying processed 213,320 tonnes of ore, down 20%, affected by safety system improvements. Production resumed and ended the quarter at a 90% operating rate.
Prices cushioned the revenue drop. The average realized silver price rose 82% to $61.83 per ounce, and the gold price rose 32% to $3,955 per ounce.
Safety upgrades at Ying are substantially completed, inspected by the government and approved to resume operations, the company said. They included tunnel enlargement and support, equipment upgrades, and halogen-free, flame-retardant power cables. About $13.4 million was spent on the works in the quarter.
GC Mine and the projects
The GC Mine has been suspended since late June 2026 because its 2014 China-standard design was not updated for changes in geology and tunneling. It processed 477 tonnes of stockpiled ore in the quarter. Silvercorp hired Changsha Institute of Mining Research Co., Ltd. to update the design, expected by the end of December 2026. Approval by the Guangdong Provincial Department of Emergency Management is expected in March 2027, and production could resume by November 2027. GC contributes less than 10% of revenue, and the company does not expect a material impact on overall results.
At the El Domo mine in Ecuador, rainfall of 620 millimetres was 489% above the six-year average, and construction was suspended during 77 days of rain. The company blamed this year's Super El Niño. It still completed about 1,009,239 cubic metres of excavation and pre-stripping.
Construction of the No. 3 mill at Ying is advancing as planned. At Kuanping, crews completed 1,507 metres of ramp development.
What to watch
Silvercorp expects to release full unaudited second-quarter results on Thursday, November 5, after the market close.
The updated GC Mine design is due by the end of December 2026, ahead of the government approval the company expects in March 2027.