Valero To Buy Lyondell's Idled Houston Refinery Site For $320.5 Million, Plans 165,000-Barrel Restart
The roughly 700-acre site sits beside Valero's own Houston refinery, and the company targets a partial restart by year-end 2027.
Valero Energy, the refiner that makes petroleum and low-carbon fuels, agreed to pay $320.5 million for LyondellBasell's former Houston refinery site, next door to its own Houston plant. It currently expects to restart 165,000 barrels per day of light sweet crude capacity by the end of 2027.
The deal and the restart plan
Valero Refining-Texas, a wholly owned subsidiary, will buy all the equity of LYB Houston Hub Holdings LLC from a LyondellBasell subsidiary, with the price subject to closing adjustments, according to the company's press release. The holding company indirectly owns an approximately 700-acre facility on the Houston Ship Channel that operated as a petroleum refinery.
Valero said it will first bring back 165,000 barrels per day of light sweet crude processing. The purchase also gives it the option to invest later in high-complexity processing of heavy sour crude.
Lane Riggs, Valero's chairman, CEO and president, called it "a unique opportunity to strategically expand Valero's U.S. Gulf Coast footprint at a fraction of replacement value." He said the deal is expected to deliver a "compelling financial return."
What Valero takes on
Valero is assuming site operations, environmental liabilities and pension costs, and the agreement continues employment for the site's workforce, LyondellBasell said.
Valero's own system, per its latest annual report as of the end of 2025, includes 15 refineries in the U.S., Canada and the U.K. with about 3.2 million barrels per day of capacity, plus the Diamond Green Diesel renewable diesel venture and 12 ethanol plants. Its press release describes the refining fleet as 14 refineries and about 3.0 million barrels per day.
Closing hinges on antitrust clearance
The sale is expected to close by the end of 2026. It requires the Hart-Scott-Rodino antitrust waiting period to expire or be terminated.
Valero expects the deal to close by the end of 2026, with the first restart capacity targeted for year-end 2027.
Sources
- 8-K Filing — VALERO ENERGY CORP/TX (VLO) — SEC EDGAR
- Exhibit a10302026exh9901pressrelea.htm — VALERO ENERGY CORP/TX 8-K exhibit — SEC EDGAR
- Valero Energy Corporation Declares Regular Cash Dividend on Common Stock – Company Announcement - FT.com — Financial Times
- LyondellBasell agrees to sell former refinery site in — globenewswire.com