Southern Copper Pushes Tia Maria Start To First Half Of 2028 As Project Spending Climbs

The copper miner's flagship Peru project is 49.6% complete, with $884.3 million invested and $1,101 million committed.

Share
Southern Copper Pushes Tia Maria Start To First Half Of 2028 As Project Spending Climbs

Southern Copper now expects its Tia Maria copper project in Peru to begin operations in the first half of 2028, a later start than the second half of 2027 given in its prior quarterly report, according to its 10-Q filed Friday. The miner, which mines, smelts and refines copper in Peru and Mexico, says the project was 49.6% complete at September 30, 2026.

A later start, a bigger bill

The prior quarterly filing put Tia Maria at 42% complete, with $693 million invested and $1,101 million committed. The new 10-Q shows $884.3 million invested against the same $1,101 million committed.

Capital spending for the first nine months of 2026 reached $1,380.5 million, against $902.7 million a year earlier. Tia Maria took $505.9 million of it, the filing shows.

On the earnings call, CFO Raul Jacob said the delay reflects extra time for mechanical assembly and engineering. He declined to confirm any increase in capital spending while budgets are under review.

Construction status

The 220 kV transmission line is nearly done, and leaching equipment has been ordered.

The company still estimates 7,000 jobs over the construction phase, up from about 6,000 in the prior filing. Tia Maria is designed to produce 120,000 tonnes of SX-EW copper cathodes a year in its early years.

The company issued $1,250 million of 5.350% senior notes due 2036 in June 2026, with proceeds earmarked for Tia Maria, its capital program and general corporate purposes.

Cash cushion and the next update

Delay or not, the quarter was strong: net income attributable to the company was $1,801.8 million, up 62.7%, on net sales of $4,696.6 million. The company says it had committed about $1,733.0 million to capital projects at September 30, 2026.

Its El Pilar copper project in Sonora, Mexico, is targeted to start production in the second half of 2029, and both projects feed its goal of 1.6 million tonnes of annual production. Market value was $161.9 billion as of Friday's close.

Management expects to provide updated Tia Maria spending projections on its January 2027 earnings call.