Rio Tinto Keeps 2026 Guidance, Cuts Lithium Outlook To Low End Of Range, And Reports Over $2 Billion In Capital Release Deals
Oyu Tolgoi copper is up 29% in the first nine months, while Sal de Vida's slow ramp-up pulls lithium toward the bottom of guidance.
Rio Tinto left its 2026 production, sales and unit cost guidance unchanged in its third-quarter production release, dated Wednesday, but said full-year lithium output is now expected at the low end of its 61 to 64 kt range. Oyu Tolgoi copper production rose 29% in the first nine months and 27% in the third quarter from a year earlier.
What the production release shows
Consolidated copper output was 205 kt in the third quarter, flat on a year earlier, against unchanged 2026 guidance of 800 to 870 kt. Oyu Tolgoi's strength was offset at Kennecott, where a flash converting furnace breach in late June cut cathode output. The company said the rebuild took about 70 days and finished at the end of August, ahead of plan.
Global iron ore sales were 90.8 Mt in the quarter, up 3% from a year earlier, with Pilbara sales up 2%. Full-year guidance for global sales of 343 to 366 Mt, and for Pilbara sales of 323 to 338 Mt, was maintained.
Simandou reached an annualised production run-rate of about 10 Mtpa on a 100% basis in the quarter. The company says it remains on track for 60 Mtpa during the second half of 2028.
Lithium carbonate equivalent production was 13.0 kt, up 4% from a year earlier and down 11% from the second quarter. The company attributed the low-end outlook mainly to a slower ramp-up at Sal de Vida, caused by available uptime of key equipment.
Capital release and costs
Rio Tinto said it has entered arrangements to release more than $2 billion of capital this year. Completion and cash receipt depend on binding agreements and conditions being met. The items include the proposed sale of the Dampier Seawater Desalination Plant, a land sale in Kitimat to LNG Canada, and a non-binding lithium sales contract with a pre-payment component. The company is working toward about $5 billion of initiatives by the end of 2026, as part of a $5 to 10 billion program.
Unit cost guidance is also maintained, though the company flagged outside pressures on Pilbara costs. Higher diesel prices added $0.9 per tonne year to date, and it expects $1.1 per tonne for the full year at a spot price of about $175 per barrel. The exchange rate adds about $1.0 per tonne at US$0.70/A$ against a guidance assumption of US$0.67/A$.
Chief Executive Simon Trott said the company remains on track for a "$1.8 billion annualised productivity benefit run-rate by the end of 2026."
What to watch
In the fourth quarter, the company expects first ore through one of the two primary crushers at the SimFer mine and through the SimFer port. A decision on development alternatives for Nemaska Lithium is also expected in the fourth quarter of 2026. The Kitimat land sale is expected to complete in the fourth quarter.
The company has said further capital release announcements are expected in 2026.