Pinnacle West Wins Approval For Cost Recovery APS Proposes Replacing With Formula Rates
The adjustment starts with December bills, while APS awaits a broader rate decision that the company estimates will come in December.
Pinnacle West Capital, the Phoenix-based electric utility holding company, said Arizona Public Service won approval Wednesday for its 2026 lost fixed cost recovery adjustment, which will take effect with December’s first billing cycle. The approval appears in handouts accompanying Friday’s SEC filing, even as APS proposes eliminating the adjustment if regulators approve its formula-rate plan.
December Bills Get The Adjustment
APS requested the cost recovery adjustment on July 31. The approval puts that mechanism into effect while the utility’s larger request to change rates remains pending.
The two proceedings have different scopes: Wednesday’s decision covers the lost fixed cost recovery adjustment; the broader case covers a proposed revenue increase and a formula for future rate updates. Pinnacle West estimates a final decision on that case in December, with regulatory dates tentative and subject to change.
A $609 Million Rate Request
APS’s broader rate proposal seeks a $609 million net revenue increase and carries a 14.69% initial customer impact. The request includes a $692 million revenue requirement increase, offset by $83 million in transfers from existing adjustment mechanisms.
APS seeks a 10.70% allowed return on equity — the return regulators permit on shareholder-funded investment. Arizona Corporation Commission staff recommends 9.55% to 9.80%, and says the commission should consider the lower end if it adopts formula rates.
Under APS’s proposed formula, rates would not change when the actual return sits within 0.40 percentage points above or below the authorized return. The plan would use a historical test year and include six months of investment in plants placed into service after that period.
APS also proposes eliminating the System Reliability Benefit and Tax Expense Adjustor Mechanism alongside lost fixed cost recovery if the formula plan is approved and retains a 120-day schedule.
APS Supplies Nearly All Earnings
Pinnacle West gets essentially all its revenue and earnings from APS, which generates, transmits and distributes electricity in Arizona. The utility served approximately 1.4 million customers and owned or leased 6,257 megawatts of regulated generating capacity at the end of 2025.
That makes the way APS recovers costs central to the parent company’s business. The rate proposal also calls for assigning generation costs directly to customers with especially high, steady electricity usage, so those customers pay for the resources they require.
December brings the approved adjustment onto bills; the broader formula-rate proposal still awaits the commission’s decision.
Sources
- 8-K Filing — PINNACLE WEST CAPITAL CORP (PNW) — SEC EDGAR
- Exhibit novemberinvestordeck.htm — PINNACLE WEST CAPITAL CORP 8-K exhibit — SEC EDGAR