Parsons Says Canadian-Style Joint Venture Is Over 75% Done, But A Slip Past June 2028 Could Cost More

CEO Carey Smith said the 50-50 infrastructure venture is exposed to weather and contract changes, with over 80% completion targeted by year-end.

Share
Parsons Says Canadian-Style Joint Venture Is Over 75% Done, But A Slip Past June 2028 Could Cost More

Parsons, which provides engineering, technology and program management services to national security and infrastructure customers, said on its third-quarter earnings call Wednesday that its critical infrastructure joint venture is now more than 75% complete. CEO Carey Smith warned that a schedule running past June 2028 "could" mean added costs or joint venture investment.

Weather, contracts and a minority seat

Smith, who is Parsons' chair, president and CEO, said the program should pass 80% by year-end and reach 85% at the end of the first quarter of 2027. She said the project remains exposed to weather, potential contract modifications and Parsons' status as the non-managing partner, though management is focused on executing to its current estimates.

The venture is 50-50, she said, and Parsons has not pursued similar consortium projects since 2019. Management has added executive oversight, increased review frequency and started critical testing and commissioning work.

Asked by a TD Securities analyst whether that meant no charge is assumed in the fourth-quarter guidance, Smith answered with a single word: "No." She said that if the schedule ran beyond June 2028 or other risks materialized, there "could be additional costs or joint venture investment required."

Resequenced work after historic rain

A UBS analyst noted that management had targeted 90% completion by year-end last quarter. Smith said historic rainfall in June and July led Parsons to resequence the work, getting to testing and commissioning sooner and pushing winter-capable tasks later. That cut costs and some headcount this year, she said, so the team can surge after the new year.

Parsons has asked the customer for relief for historical weather and other events. That relief is not included in the forecast completion date of June 2028, Smith said. She expects the nature and impact of remaining issues to be less significant than in the past as the project nears completion.

Quarter and guidance backdrop

Parsons narrowed its 2026 outlook to revenue of $6.25 billion to $6.45 billion and adjusted EBITDA of $510 million to $550 million, and kept operating cash flow guidance at $430 million to $490 million. Third-quarter operating cash flow was $269 million, and total backlog reached a record $9.4 billion. The company also said Chief Financial Officer Matt Ofilos is stepping down and former CFO George Ball will become interim CFO effective November 6.

Smith said management should have better visibility on contract protests by its fourth-quarter report, when it plans to give full-year 2027 guidance in February 2027. Market value was about $5.4 billion in Wednesday morning trading.

Parsons will give full-year 2027 guidance on its fourth-quarter call in February 2027.