NextEra Says Three Data-Center Hubs Worth 16.5 Gigawatts Pay Fees, Not Capital Bills

CEO John Ketchum also defended the pending Dominion merger against Virginia opposition on the third-quarter call.

Share
NextEra Says Three Data-Center Hubs Worth 16.5 Gigawatts Pay Fees, Not Capital Bills

NextEra Energy has signed definitive agreements for three "federal hubs" in Texas and Pennsylvania totaling about 16.5 gigawatts, CEO John Ketchum said on the company's third-quarter earnings call on Wednesday. He said the projects have secured $5.7 billion in initial funding this year, and that NextEra's Energy Resources unit earns fees on them without investing capital.

How the hub fees work

Ketchum said Energy Resources is paid on a predetermined schedule for development, construction and the first 20 years of operation. He said the hubs should generate about 50% of the adjusted earnings per share the company would receive if it owned the projects itself.

On that equivalent-earnings basis, he said, the three hubs roughly match the top end of the company's 4 to 8 gigawatt natural gas development expectations for 2032. He said NextEra could also build and own battery storage at the sites, an incremental 6 to 11 gigawatts, or roughly 15% to 30% upside to its storage development expectations.

Early money is small. CFO Mike Dunne called the 2026 and 2027 payments "relatively modest," growing through 2032, when operating fees begin. Those fees run from 2032 to 2052 and should be roughly half the earnings per share of owning the facilities, he said.

Asked by a Barclays analyst whether less gas capital spending means fewer asset sales, Dunne said the base plan does not rely on capital recycling to meet equity needs. He said he expects to hold more of the $7 billion to $12 billion of recycling, and would sell only if a buyer values an asset far above the company's own view.

Dominion and Virginia

Asked about filings from the Virginia governor's office and staff, Ketchum pointed to hearings in mid-November and a rebuttal due in a couple of weeks. On the state's do-no-harm standard he said, "I like our chances," adding that the decision is for regulators.

He cited almost $2 billion in rate credits before the Virginia commission and an enhanced package announced in September. It includes doubling residential bill credits from two to four years, $100 million more for customer bill assistance through 2038, and 1,000 new Virginia jobs.

Dunne said NextEra's 8% plus earnings growth target would be 9% plus in combination with Dominion, pointing to the S-4 merger filing. Ketchum said shareholders of both companies approved the deal on September 3, and he continues to expect closing in the second half of 2027.

What to watch

In Virginia and South Carolina, hearings are set for November and December, with final orders expected in January 2027. North Carolina expert hearings begin in February 2027.

Florida's FPL chief executive Scott Borries said the company remains confident of announcing a large-load deal by year-end, and declined to give its size. Dunne said the 2026 adjusted earnings range of $3.92 to $4.02 is unchanged, with the high end targeted. NEE shares were down 0.65% at $78.35 in Wednesday trading.

The next dated checkpoint is the mid-November Virginia hearings, ahead of the January 2027 orders in Virginia and South Carolina.

Sources

More on NextEra Energy

All NextEra Energy (NEE) coverage →