Idacorp Says 5 Gigawatts Of Prospective Big-Customer Load Is Still Preliminary, Beyond Its 8.9% Forecast

Executives laid out tiers of prospective customers outside the 8.9% load forecast, and gave no firm date on a Micron Fab 2 contract.

Share
Idacorp Says 5 Gigawatts Of Prospective Big-Customer Load Is Still Preliminary, Beyond Its 8.9% Forecast

Idacorp, the holding company for electric utility Idaho Power, told analysts on its third-quarter earnings call Thursday that about five gigawatts of prospective large-customer projects are still preliminary, all of it outside the 8.9% annual retail load growth forecast it uses for planning. Chief Operating Officer Adam Richins said a further gigawatt is "promising" and another is in a paid study phase.

Tiers of a four-gigawatt pipeline

Richins said the roughly four-gigawatt pipeline leaves out Micron Fab 1 and Meta's first data center, so it is "truly a future pipeline." About one gigawatt is promising, which usually means a financial commitment and a move toward construction. Another gigawatt is being studied, with no major commitments yet but with the customers paying for the studies.

About two gigawatts felt preliminary, Richins said, but three more gigawatts have arrived since the four-gigawatt figure was first cited. "Really five gigawatts are preliminary," he said.

CEO Lisa Grow said the pipeline sits "right about 4,000 megawatts." She added that it is not the same 4,000 as on earlier calls, because projects that enter construction move out as new ones come in. Idacorp has received 76 inquiries in 2026 from projects needing more than one megawatt, which Grow said is on pace for another historically busy year.

What the 8.9% forecast includes

The preliminary 8.9% five-year growth rate in retail sales for the 2027 resource plan rises from about 19,000 gigawatt hours in 2027 to about 29,000 by 2032, Grow said. Richins said it includes Micron's Fab 1 and Fab 2, Meta's first data center, an unnamed data center, Perpetua, INL and Chobani. It leaves out a possible Micron Fab 3 or other data centers.

Grow said Meta's data center south of Boise began operating in September. Industrial revenues rose 27% from last year's third quarter. Nine-month earnings reached $5.76 a share versus $5.13, and 2026 guidance now stands at $6.40 to $6.50.

Micron Fab 2 contract stays open

A Barclays analyst asked whether an energy service agreement for Micron Fab 2 would be signed within the next couple of months. Grow said talks are going well, the company is hopeful of meeting its timelines, and "we'll certainly see the filing when we do."

On the build-out, Grow said Idacorp expects to move ahead with selected 2032 RFP projects by year-end, so regulatory filings should follow. Chief Financial Officer Brian Buckham said an updated capital spending forecast will come on the fourth-quarter call.

Buckham said Idacorp is running numbers on a possible June 2027 rate case filing, and the fourth-quarter call may offer a preliminary read.