Hudbay Defends $200 Million In Copper World Spending To Avoid Lengthy Expansion Shutdowns

Outside funding would defer Hudbay's first capital contribution to 2028, with its share expected to be roughly $500 million.

Share
Hudbay Defends $200 Million In Copper World Spending To Avoid Lengthy Expansion Shutdowns

Hudbay Minerals, an Americas-focused copper producer, is spending approximately $200 million on Copper World design changes partly to avoid lengthy shutdowns when the Arizona mine expands. Chief Executive Officer Peter Kukielski explained the spending on the company's earnings call Thursday, calling the additions “no regrets changes to the scope.”

Building For A Larger Copper Plant

A Barclays analyst asked how the added spending would benefit expansion and whether it could help with Hudbay's Cactus and Mason projects. Kukielski's answer focused on preparing Copper World for growth without taking the operation offline for “weeks or months at a time.”

Processing equipment accounts for roughly $60 million of the changes. The work includes upgrades to the primary crusher, larger pumps, an upgraded ball mill and room for a bigger grinding circuit. Tailings storage accounts for about $50 million, mine development and earthworks roughly $40 million, and indirect costs about $50 million.

Hudbay plans to install an in-pit crushing and conveying system in year four, then increase the processing plant's daily capacity to 90,000 tons from 60,000 in year five. Management projects average annual copper output of 120,000 tons in years six through 10, a 43% increase over the first five years.

Compared with the 92,000 tonnes of average annual copper production over the first 10 years anticipated in the 2023 preliminary study, the design already puts expected output for that period at 102,000 tonnes.

Partners Carry Much Of The Funding

Mitsubishi, Hudbay's Copper World joint venture partner, closed its investment in January 2026, according to Hudbay's results release. The partners approved construction in October, when Hudbay also filed the project's technical report.

Kukielski put initial growth capital at $2 billion, including the approximately $200 million of scope changes. The funding plan includes Mitsubishi's $600 million initial investment and a $230 million deposit from Wheaton under a metals-streaming agreement. Hudbay plans to arrange up to $650 million in project-level debt financing.

Management expects Hudbay's own contribution to be roughly $500 million, starting in 2028 and representing less than 25% of initial growth capital. With copper priced at $5.00 per pound, Hudbay's projected base-case return after borrowing rises to 32% because of the funding structure, Kukielski said.

Construction preparations are underway. Kukielski said the water pipeline was about 60% complete, with all its material on site, and Hudbay had committed to the required truck fleet.

Lower Costs At Existing Mines

Hudbay also improved its outlook for 2026 copper cash costs to negative $0.55 to negative $0.35 per pound, a further $0.10 improvement. Those costs include credits from other metals; Kukielski attributed the improvement to operating efficiencies and gold credits that more than offset external cost pressures.

The company generated $202 million of free cash flow in the third quarter, approximately $100 million more than in the second quarter. Free cash flow exceeded $400 million for the first nine months, after more than $325 million of sustaining capital spending.

Hudbay targets Copper World's first production for the second half of 2029. Management expects the project to double the company's current annual copper production to approximately 250,000 tons.