Granite Pushes $569 Million Of Tactical Infrastructure Backlog To 2028, Says Profit Outlook Holds
The CEO said right-of-way availability stretched the projects, while a 4,500-acre Southern California rail job awaits permits.
Granite Construction, which builds roads, bridges, rail and other infrastructure and produces construction materials, now expects its $569 million of tactical infrastructure backlog to be finished in the third quarter of 2028, not the second quarter of 2027, CEO Kyle Larkin said on the company's third-quarter earnings call Thursday.
Longer timeline, same profit view
The $569 million sits inside $1.3 billion of federal backlog at quarter end. Larkin said the new date reflects current right-of-way availability, and that while the projects will take longer, management's expectations for their overall success and profitability are unchanged.
Asked about how fast backlog converts to revenue, Larkin said Granite typically burns 40% to 50% of its year-end backlog. Because of the border infrastructure work, he said, next year could land at 45% to 50%, though the year-end balance is not yet known.
Total backlog rose $37 million from the prior quarter to a record $7.5 billion, Larkin said. Federal work is expected to be about 15% of construction segment revenue this year.
A rail project waiting on permits
Larkin said Granite is in pre-construction with a Class I railroad on a 4,500-acre intermodal project in Southern California, meant to expand capacity on an east-west freight corridor and ease the movement of freight from the ports of Los Angeles and Long Beach. The project remains subject to permitting.
If it advances to construction, Larkin said, it could be a meaningful opportunity beginning in 2027 and ramping in 2028. He said rail is under 5% of construction segment revenue today, could be closer to 5% in 2027 depending on timing, and could approach 10% by 2028.
Quarter and targets
Third-quarter revenue rose 23% to $1.8 billion from a year earlier, and adjusted EBITDA rose $67 million to $283 million, CFO Staci Woolsey said. Mission-critical infrastructure backlog, tied to data centers, battery storage and space clients, was about $331 million.
Granite raised the low end of its 2026 revenue range to $5.4 billion from $5.3 billion, keeping the top at $5.5 billion. Management also targets an adjusted EBITDA margin of 14% to 16% in 2029, with organic revenue growth of 10% to 12% a year through then.
Larkin said the Southern California rail project's permitting determines whether it advances to construction, which he said could begin to matter in 2027.
Sources
- Granite Construction (NYSE:GVA) delivers impressive Q3 2026, full-year outlook slightly exceeds expectations — Yahoo Finance
- Granite Construction Non-GAAP EPS of $3.81 beats by $0.48, revenue of $1.8B beats by $100M (GVA:NYSE) | Seeking Alpha — seekingalpha.com
- Granite Construction (GVA) Q3 Earnings and Revenues Beat Estimates — Yahoo Finance
- Granite Construction: Q3 Earnings Snapshot | wusa9.com — Associated Press
- Granite Construction Q3 2026 Earnings Preview | Seeking Alpha — seekingalpha.com