Galaxy Walked Away From A Helios 2 Lease This Summer — Novogratz: 'We're Not Going To Compromise'

Galaxy's CEO said it was in advanced talks but turned down the terms, betting scarcer power and tighter financing strengthen its hand.

Share
Galaxy Walked Away From A Helios 2 Lease This Summer — Novogratz: 'We're Not Going To Compromise'

Galaxy Digital was deep in talks for a Helios 2 lease this summer and chose not to sign, CEO Mike Novogratz said on the company's third-quarter earnings call Tuesday. "We're not going to compromise on terms just to meet an announcement date," he said, after floating a summer agreement earlier this year.

A deal management says it could have signed

Novogratz said the company was in advanced discussions, but the market shifted materially in late summer and Galaxy decided against the terms on the table. He said the market for large-scale data center power has grown more constrained while demand for capacity from 2028 onward has strengthened.

President Chris Ferraro put it bluntly when an analyst from Morgan Stanley asked what stands in the way. "We could have signed a deal had we wanted to," he said, adding that Galaxy "proactively chose not to" because of the change in market dynamics.

Answering an analyst from Piper Sandler, Ferraro said projects nearby were being delayed and regulatory pressure was tightening. Financing structures such as investment-grade wraps around weaker counterparties looked interesting, he said, but "the devils are in the details," and a wrap that does not protect both debt and equity "isn't really an investment-grade wrap."

Mid-2028 energization and a 'lot of cushion'

Pressed by an analyst from Compass Point on whether the timeline slips, Ferraro said Helios 2 is expected to be energized in mid-2028. Working back, he said, that leaves roughly 1.75 years of room, which he called "a lot of cushion."

Talks now center on investment-grade hyperscalers or counterparties backed by investment-grade credit enhancement. Novogratz said Helios 2 has more than 800 megawatts of secured power.

Ferraro said Galaxy has committed approximately $230 million in deposits and purchase orders for long-lead electrical equipment for Helios 2.

Texas dates tenants are watching

Ferraro named two dates on prospective tenants' minds: December, when Galaxy expects clarity on audit results submitted across its assets including Helios 2, and April 2027, when it expects ERCOT Batch Zero study-load power allocations.

Galaxy, which runs a digital-asset financial services business and develops the Helios data center campus in West Texas leased to CoreWeave, is separately building Helios Phase 2, which Ferraro said adds 260 megawatts, is fully funded and is under construction. Data hall deliveries start in the second quarter of 2027. Novogratz said Helios is generating about $80 million of leasing revenue per quarter from phase one.

Novogratz said Galaxy expects to exit 2027 at an annualized leasing revenue run rate of between $800 and $850 million, based on current delivery schedules.