FirstEnergy Says Contracted Large-Load Demand Nearly Doubled To 7.9 Gigawatts, Pointing To Bigger Transmission Plan
The Akron utility earned $0.96 per share in the third quarter and kept its 2026 Core Earnings outlook, with a West Virginia gas plant order due.
FirstEnergy, the Akron, Ohio utility, said Tuesday that contracted demand from large customers has reached 7.9 gigawatts, nearly double the level at the start of the year, and that it expects to raise its $19 billion transmission plan by at least 25% when it rolls the plan forward. The company also reported third-quarter earnings of $557 million, up from $441 million a year earlier.
Earnings climb on higher revenue
FirstEnergy, which delivers electricity to more than 6 million customers across Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York, earned $0.96 per share on revenue of $4.6 billion. A year earlier it earned $0.76 per share on revenue of $4.1 billion.
Core Earnings, the company's adjusted measure that excludes items management considers unusual, were $0.98 per share against $0.83 a year earlier. For the first nine months, Core Earnings were $2.20 per share, up 9% from $2.02.
The company reaffirmed its 2026 Core Earnings guidance of $2.62 to $2.82 per share and said it expects results at or slightly above the midpoint. It also kept its long-term growth rate near the top end of 6% to 8% through 2030. In the first nine months, it put $4.9 billion into Energize365, its five-year, $36 billion investment plan.
Chairman, President and CEO Brian X. Tierney said, "We're delivering on our commitments while positioning FirstEnergy for the next phase of growth."
Transmission plan set to grow
Beyond the 7.9 gigawatts already contracted, FirstEnergy is in active negotiations for about 4 gigawatts more. The company said those demands, together with infrastructure needed to support the regional grid, are expected to lift its 2026–2030 transmission plan by at least 25% when it rolls forward to 2027–2031. Its network sits in the heart of PJM, the grid operator serving more than 65 million people.
In its investor slides, the company says it plans to fund up to 35% of the incremental investment with equity or equity-like content. It expects to roll the plan forward in February 2027.
A gas plant in West Virginia
FirstEnergy has reserved turbines from Siemens for the proposed Maidsville Energy Center, a combined cycle gas plant in West Virginia, with delivery expected in 2030. It projects a final order from the West Virginia Public Service Commission in the fourth quarter of 2026.
Tierney called Maidsville "the first of a broader set of opportunities in West Virginia." The slides say the company is negotiating with a data center customer to buy the plant's output over the long term, and has issued an initial request for proposals for another 3 gigawatts of gas turbines, with an update expected in early 2027.
FirstEnergy holds its earnings webcast at 9 a.m. EDT on Wednesday.
Sources
- 8-K Filing — FIRSTENERGY CORP (FE) — SEC EDGAR
- Exhibit ex991-q32026newsrelease.htm — FIRSTENERGY CORP 8-K exhibit — SEC EDGAR
- Exhibit ex992-3q26festrategicand.htm — FIRSTENERGY CORP 8-K exhibit — SEC EDGAR
- FirstEnergy Non-GAAP EPS of $0.98 beats by $0.08, revenue of $4.6B beats by $310M (NYSE:FE) | Seeking Alpha — seekingalpha.com
- FIRSTENERGY DELIVERS STRONG THIRD QUARTER RESULTS, BUILDS MOMENTUM FOR LONG-TERM GROWTH — prnewswire.com