FirstEnergy Raises Earnings Growth Target To 7%-9% As Its Investment Plan Expands

The utility's five-year investment plan rose to $38 billion, and anticipated equity financing increased to $2.8 billion.

Share
FirstEnergy Raises Earnings Growth Target To 7%-9% As Its Investment Plan Expands

FirstEnergy, which supplies electricity through regulated utilities, raised its annual adjusted earnings-per-share growth target Friday to 7%-9% from 6%-8% for 2026-2030. The company said in its SEC filing that West Virginia's approval of the Maidsville generation project prompted the increase in its investment plan.

More Investment, More Equity Financing

FirstEnergy now plans to invest $38 billion over 2026-2030, versus $36 billion previously, including about $2 billion for Maidsville within that period. Management is targeting the upper half of its revised earnings-growth range.

Anticipated equity financing increased to $2.8 billion from $2 billion. FirstEnergy plans to cover approximately 35% of Maidsville's investment through equity or securities with equity characteristics.

The company raised its projected annual growth in rate base—the investment on which regulated utilities can earn returns—to 11.1% from 10.4%. Management expects earnings growth to accelerate over the planning period as Maidsville spending progresses.

West Virginia Adds Gas And Solar

The Public Service Commission of West Virginia approved the project Tuesday for FirstEnergy's Mon Power and Potomac Edison utilities. It includes a 1,200-megawatt natural-gas plant in Maidsville and 70 megawatts of solar at Davis, Wylie Ridge and Valley Point.

A new surcharge permits recovery in cash of financing costs during construction. The order also allows contracts intended to protect other customers from subsidizing the investment needed to serve new large electricity users.

The project's previously outlined estimated total cost is $2.7 billion: $2.5 billion for the gas plant and $0.2 billion for solar. FirstEnergy's investor presentation lists December 31, 2031, as the gas plant's planned operating date and 2027-2030 for the solar facilities.

FirstEnergy is seeking a low-interest Department of Energy loan. It estimates customer savings of about $217 million for each $1 billion of guaranteed borrowing over a 30-year term.

Grid Spending Meets Data-Center Demand

The revised plan includes $9 billion for infrastructure renewal, 28% above the previous five-year plan. Another $6 billion is allocated to grid modernization, up 20%, including improved circuit protection and advanced meters. Transmission accounts for $19 billion, and New Jersey energy-efficiency commitments account for $1.2 billion.

Akron, Ohio-based FirstEnergy serves more than six million customers across Ohio, Pennsylvania, West Virginia, Maryland, New Jersey and New York. Its businesses span distribution networks, regulated generation and more than 24,000 miles of transmission lines; government regulators set their rates.

Contracted data-center demand had nearly doubled to about 7.9 gigawatts, alongside 19 gigawatts of potential demand. FirstEnergy invested $4.9 billion in the first nine months of 2026.

Third-quarter adjusted earnings reached $0.98 per share, up about 18% from a year earlier. FirstEnergy attributed the growth to customer-focused investment, greater demand and better operating performance.

FirstEnergy expects to sign gas-supply and engineering-and-construction contracts in the fourth quarter of 2026. Site preparation is expected to begin in the first quarter of 2027.