Fervo Cuts Spending Forecast To $700 Million–$750 Million — Its Plant Schedule Stays Intact

Construction efficiencies push some spending later, while the third-quarter operating loss widens to $43.7 million.

Share
Fervo Cuts Spending Forecast To $700 Million–$750 Million — Its Plant Schedule Stays Intact

Fervo Energy, which builds and operates geothermal power plants, cut its second-half capital-spending forecast to $700 million–$750 million from $850 million–$900 million in the earnings release accompanying Monday's SEC filing. Management attributed the reduction to construction efficiencies that move spending later, while keeping expected plant completion dates and total investment unchanged.

Later Spending, Same Cape Schedule

Fervo expects fourth-quarter capital spending of approximately $450 million–$500 million. It spent $256.7 million in the third quarter, mostly at Cape Station, compared with $226.5 million in the second quarter, according to its earnings release.

The spending shift concerns Cape Google 400, the generating blocks intended to supply Google's contracted power. Drilling is approximately 18% complete; the first 50-megawatt turbines passed factory testing, and more than 60% of the air-cooled condensers have reached the site. Fervo targets an installed cost of $5,500 per kilowatt, versus its longer-term target of $3,000.

Cape Station's second block is exporting test electricity. The third is mechanically complete, with mechanical and electrical equipment being tested before geothermal fluid enters the system. Fervo also began installing an on-site solar array to supply auxiliary power.

Tim Latimer, Fervo's CEO and co-founder, said the company is focused on “delivering the remaining Phase I GeoBlocks on schedule” in the earnings release.

Operating Loss Widens As Costs Rise

Fervo's unaudited third-quarter operating loss was $43.7 million, against $13.659 million a year earlier. Administrative expenses reached $39.4 million, compared with $27.4 million in the second quarter; management cited increased stock compensation, public-company costs and workforce growth.

Revenue was $116,000, up from $55,000 a year earlier. Net income of $11.7 million included $15.4 million in interest income, a non-cash $11.8 million gain on interest-rate swaps and a $29.9 million tax benefit from credits earned when Cape Phase I assets entered service. Common stockholders nevertheless recorded a $20.8 million loss, or $0.07 per share.

Fervo finished the quarter with $1.9 billion in unrestricted cash and cash equivalents and $301.6 million in debt. Management kept its fourth-quarter revenue expectations and 2027 revenue outlook unchanged; the fourth quarter will be Cape Station's first full quarter of revenue.

Google Commitments And A Larger Resource

Fervo uses horizontal wells and hydraulic fracturing to connect hot rock underground, allowing water to bring heat to the surface. Cape Station in Utah is its 500-megawatt development; Project Red in Nevada has supplied 3 megawatts to the grid since 2023.

On September 1, Fervo announced a Google agreement for 396 megawatts. The 15-year contract requires Google to pay for the agreed power whether it takes delivery or not, with first power expected in mid-2028 and full capacity targeted by year-end 2028. Google will also be offered an approximately 600-megawatt expansion option under the companies' framework for up to 3 gigawatts through 2033.

On October 1, Fervo announced that Cape Station's first plant had entered commercial operation and produced 33 megawatts net. Operating capacity reached 36 megawatts, from 3 megawatts at the second quarter's end. Binding power contracts now cover 1,054 megawatts and approximately $11.9 billion in contracted revenue, versus 658 megawatts and approximately $7.2 billion at the second quarter's end.

An independent DeGolyer and MacNaughton study estimates approximately 8.4 gigawatts of capacity potential at Cape Station, nearly double the prior 4.3-gigawatt estimate. Fervo attributed the increase to deeper planned wells and additional leases. It was also selected for two potential Energy Department awards totaling approximately $20 million for appraisal wells in Idaho and Nevada, pending definitive funding agreements.

Fervo expects the second and third Cape Station blocks to enter commercial operation by January 1, 2027, completing Phase I.