EMCOR CEO Predicts Data Center Politics Will Fade 'Magically' After The Election

Tony Guzzi says moratorium talk and Loudoun's pause won't derail awards, with data centers about a third of year-to-date revenue.

Share
EMCOR CEO Predicts Data Center Politics Will Fade 'Magically' After The Election

EMCOR Group CEO Tony Guzzi told analysts on the company's third-quarter earnings call Thursday that political rhetoric against data centers will die down "magically between November 3rd and November 30th post-election." EMCOR, which designs, installs and maintains electrical and mechanical systems in buildings and plants, has data centers at roughly a third of its year-to-date revenue, so the politics matter to it.

Moratorium talk, in Guzzi's words

Asked by a William Blair analyst whether moratorium politics had delayed projects or pipelines, Guzzi, EMCOR's chairman, president and CEO, said no. Most of what gets built over the next two or three years, he said, is not subject to that rhetoric, which concerns projects being permitted for 18 to 24 or 36 months out. He added that a lot of it "wasn't grounded in fact."

The political discussion, Guzzi said, targets AI data centers specifically. On candidates pushing moratoriums, he said they are "one senator of 100, regardless of what they want."

EMCOR shares rose 5.79% to $717.81 in Thursday trading.

Loudoun pause and Virginia

A Goldman Sachs analyst called Virginia EMCOR's top market and asked about the pause Loudoun County recently enacted on data centers. Guzzi said the company is bullish on Virginia and fully expects new Loudoun awards by the middle of next year.

Loudoun, he said, was booked for the next two or three years anyway. The pause was probably about deciding where else to build in the county, and about waiting for power to be provided.

Guzzi also said part of the policy response made sense. He cited a fair amount of phantom demand in Texas and said some of it will lengthen the cycle, which he called a good thing.

Cloud-heavy mix, concentrated exposure

Management said data centers could approach 50% of EMCOR's construction revenue. Guzzi said the company works for large hyperscalers and those serving them, and is not much into the neocloud market or speculative builds.

He estimated today's data center mix at 65% to 70% cloud and about 30% AI, and said it will probably move toward 50-50 in the future. CFO Jason Nalbandian said the customer base is diverse, with the data center third of revenue split among numerous companies.

Data center backlog hit a record $8.74 billion, more than double the year-ago level, in a quarter where total remaining performance obligations reached a record $18.57 billion.

Guzzi's own test is dated: new Loudoun County awards by the middle of next year.