DT Midstream Approves A 300 MMcf/D Midwestern Expansion And A 900-Megawatt Power-Plant Lateral
The pipeline operator also raised its 2026 adjusted EBITDA outlook and said it is working on the next phases for 2030 and 2031.
DT Midstream, which owns natural gas pipelines, storage and gathering systems, has given the go-ahead to a 300 MMcf/d expansion of its Midwestern pipeline to serve Indiana power demand, President and COO Chris Zona said on the company's Thursday earnings call. Zona added that the company is now progressing the next phases for 2030 and 2031.
A 20% jump in Midwestern capacity
Zona said the first phase, called MIST Southbound Phase 1, adds about 300 mmcf per day, a 20% increase in the pipeline's total capacity. Investment-grade utilities have signed 20-year negotiated rate contracts for it, and service is expected in the fourth quarter of 2029.
The company also reached a final investment decision on a lateral serving a new 900-megawatt power plant that is still under development. It carries a 20-year demand-based contract with a utility and is expected in service in the first half of 2028.
CFO Jeff Jewell said the two Midwestern projects together need $275 to $325 million of investment, at what he called an attractive build multiple. The company said it expects the primary receipt point on the new contracts to be REX.
Slater keeps the next phase vague
Zona said the company's view of the broader MIST opportunity and the size of potential investment "has not changed." A Wells Fargo analyst noted the spring open season drew 1.5 BCF per day of interest and said a second southbound phase looked like it could be larger than the first.
Chairman and CEO David Slater answered that "nothing has changed" and that the company is in "execution mode." Pressed on supply sources and whether Vector 2030 is tied commercially to the next phase, he said the company would not "dive into the nuts and bolts" for competitive reasons. He called the new expansion "very encouraging."
Zona said lateral solutions are part of some of the 2030 and 2031 discussions as well.
Raised guidance and lower growth spending
Jewell said third-quarter adjusted EBITDA was $301 million, down $4 million from the prior quarter, and that the fourth quarter should be lower on offline capacity and incremental expenses at Stonewall and lower Northeast volumes from producer curtailments. DT Midstream raised the midpoint of its 2026 adjusted EBITDA guidance and narrowed the range to $1.185 to $1.225 billion. It raised its distributable cash flow range to $860 to $890 million and cut 2026 growth capital to $375 million to $425 million.
The company reached a decision on approximately $0.4 billion of new projects in the quarter. Total committed capital is about $2.4 billion, or 70% of its five-year organic project backlog. The quarterly dividend stayed at 88 cents per share. The company's market value was $12.7 billion in Thursday morning trading.
Management will formally update its project backlog on the 2026 year-end call, and it is progressing the Millennium Ramapo open season, which targets service in the fourth quarter of 2028.
Sources
- DT Midstream: Q3 Earnings Snapshot – WTOP News — wtop.com
- DT Midstream (NYSE:DTM) : Articles :: Law360 — law360.com
- DT Midstream Reports Strong Third Quarter 2026 Results; — globenewswire.com