Dominion's CFO Shows The Day-Count Behind Its Offshore Wind Deadline: 30 To 95 Spare Days

On the earnings call, CFO Steven Ridge laid out the schedule math for 132 remaining turbines while CEO Bob Blue sidestepped merger-condition questions.

Share
Dominion's CFO Shows The Day-Count Behind Its Offshore Wind Deadline: 30 To 95 Spare Days

Dominion Energy's offshore wind schedule holds between 30 and 95 days of slack, CFO Steven Ridge told analysts on the company's third-quarter earnings call on Friday, as CEO Bob Blue declined to get into regulators' conditions for the proposed NextEra Energy merger.

The turbine-by-turbine arithmetic

Dominion Energy, the Richmond, Virginia, utility that serves about 4.1 million customers in Virginia, North Carolina and South Carolina, has about 425 calendar days left through the end of 2027 to install the remaining 132 turbines at its Coastal Virginia offshore wind project, Ridge said. That works out to about 3.2 calendar days per turbine, he noted, which happens to match the pace of the last three months.

Those three months spanned about 91 days, of which 14 were hit by weather and about 36 by vessel maintenance. The crew installed about 13 turbines over roughly 41 available days.

Ridge walked through the forward plan. At the base assumption of two days per turbine, installation takes 265 days. At a day and a half, the pace of the most recent nine turbines, it takes about 200 days. Port turns add about 130 days, from about 33 loadouts at roughly four days each. After subtracting those, Ridge said, between 30 and 95 days remain for weather, maintenance and harder locations.

Blue added that the first 10 turbines took an average of 69 hours each to install, the next 25 averaged 45 hours, and the most recent nine averaged 38 hours, a 45% improvement over the first 10.

Project status and the budget

Blue said the project is about 85% complete, with 44 turbines installed, representing more than 640 megawatts, and the 45th underway. July and August installation ran in line with expectations, he said, while September and October fell short because of weather and vessel maintenance, which finished earlier this month.

The outlook is unchanged, Blue said: completion by the end of 2027 and energization of the third offshore substation by year-end 2026. The budget stays at $11.65 billion, including $123 million of unused contingency.

Silence on staff's merger conditions

A Wells Fargo analyst asked which of the 57 staff conditions in Virginia were deal breakers. Blue said a chunk were conditions Dominion had already proposed voluntarily, and that the focus is the statutory "no harm" standard.

An Evercore ISI analyst asked what regulators want from ring-fencing. Blue said he did not want to get into details "on the Friday before we file our rebuttal testimony."

Rebuttal testimony in Virginia is due Monday, evidentiary hearings begin November 17, and a final order is due by January 11 of next year. Blue said the deal is still expected to close in the second half of 2027.

Guidance and data center demand

Ridge said Dominion now expects full-year operating earnings in the top half of its original guidance range, and reaffirmed its other financial guidance. Third-quarter operating earnings were $1.28 per share, including five cents from renewable natural gas tax credits and five cents from better-than-normal weather.

The company has over 54 gigawatts of data center capacity in various stages of contracting, including over 12 gigawatts under electric service agreements.

Dominion files its Virginia rebuttal testimony Monday, and hearings begin November 17.