CenterPoint's Houston Data-Center Queue Shrinks By About 2 Gigawatts As Customers Take Back $135 Million

The utility lifted its 10-year capital plan by $4 billion, but its quarterly report shows large-load customers pulling money out.

Share
CenterPoint's Houston Data-Center Queue Shrinks By About 2 Gigawatts As Customers Take Back $135 Million

CenterPoint Energy, the Houston-based utility holding company, returned about $135 million to large-load customers in the third quarter, and its Houston grid unit now counts 10 gigawatts of base load plus roughly two of studied load in the Texas grid's Batch Zero queue, down from about 14 gigawatts originally submitted, according to its 10-Q filed Tuesday.

Deposits in, deposits out

Customers put up about $290 million in construction contributions and about $600 million in financial security with Houston Electric during the quarter. Of that, about $135 million went back to large-load customers.

The prior quarter's filing described roughly $900 million as provided or committed, "a portion of which may be returned." The new report records an actual return.

The 10-Q says the amounts will keep shifting as projects move through grid-operator reviews and customers either advance toward construction or leave the process. Houston Electric also said the gigawatts that ultimately connect, and when, remain uncertain.

A bigger plan, same day

CenterPoint raised its 10-year capital plan by $4 billion, to about $70.7 billion through 2035. In its earnings release, it reported third-quarter net income of $331 million, or $0.50 per diluted share, against $0.45 a year earlier.

CEO Jason Wells said the Greater Houston region's "speed-to-market advantage" is creating a pipeline of additional customer-driven investment.

The company's electric segment includes Houston Electric, which delivers power along the Texas Gulf Coast, and Indiana Electric. Its natural gas arm serves customers in Indiana, Minnesota, Ohio and Texas.

Funding the build

On September 9, the company replaced its credit lines with four facilities totaling $4.6 billion. As of October 21, $173 million of commercial paper was drawn.

In August it issued $700 million of 6.400% junior subordinated notes due 2058. It also closed the sale of its Ohio gas business on October 1.

On the Houston rate case over its temporary emergency generators, a judge filed a revised proposed order on October 9. It still awaits a spot on the Public Utility Commission of Texas agenda.

The next quarterly report will show whether more large-load money flows back out as customers advance or exit the queue.