Revenue edged up 1% to C$619 million, and the uranium producer narrowed its 2026 output and delivery ranges.

Share
Cameco's Third-Quarter Adjusted Result Turns To A C$2 Million Loss As Deliveries Fall

Cameco, the uranium producer that owns 49% of Westinghouse, posted a third-quarter adjusted net loss of C$2 million, against adjusted earnings of C$32 million a year earlier, in results released Thursday and filed Friday. Revenue edged up 1% to C$619 million, while net earnings attributable to equity holders were C$43 million, against nil a year earlier.

Lower volumes, higher costs

Cameco said results for the quarter and the first nine months were generally lower than in 2025, mainly because of lower equity earnings from Westinghouse, lower sales volumes and a higher average unit cost of sales, partly offset by higher realized prices. Adjusted EBITDA fell 14% to C$267 million.

In the quarter itself, Westinghouse improved: Cameco's share of its net loss narrowed to C$24 million from C$32 million, and its share of adjusted EBITDA rose to C$143 million from C$124 million. The weakness shows up over nine months, where Westinghouse posted a C$80 million loss (Cameco's share) against C$32 million of earnings a year earlier. Cameco ties that to the Dukovany reactor construction project, which added about US$170 million to its share of Westinghouse's 2025 second-quarter revenue.

For the first nine months, net earnings attributable to equity holders fell 49% to C$199 million, adjusted net earnings fell 32% to C$279 million, and cash provided by operations dropped 85% to C$112 million. Cash from operations in the third quarter alone was C$3 million, down from C$156 million.

Uranium segment and Key Lake shutdown

In the core uranium segment, third-quarter earnings before taxes were C$175 million and adjusted EBITDA was C$179 million, against C$172 million and C$220 million a year earlier. Cameco attributed that to normal quarterly delivery swings and lower planned 2026 delivery volumes. It delivered 5.6 million pounds in the quarter.

The annual maintenance shutdown at the Key Lake mill began in the third quarter and was planned to run longer than in past years because of new infrastructure and major repairs.

Guidance trimmed, costs raised

Cameco narrowed 2026 production guidance to 19.5 million to 20.5 million pounds, from 19.5 million to 21.5 million, and delivery guidance to 29.5 million to 30.5 million pounds, from 29 million to 32 million. It raised its average unit cost of sales outlook to C$67.00 to C$70.00 a pound, from C$63.00 to C$67.50, citing the narrower production range and inflation.

Capital spending guidance fell to C$440 million to C$490 million, from C$490 million to C$540 million. The company also lifted its direct administration cost outlook to C$260 million to C$280 million.

Cash stood at C$860 million at September 30, against C$1.0 billion of total debt and an undrawn C$1.0 billion credit facility. The board declared a C$0.24 annual dividend, payable December 15 to holders of record on November 30.

Port Hope conversion relicensing hearings are scheduled for the fourth quarter, with the facility's current operating licence expiring in February 2027.