BHP Keeps Fiscal 2027 Copper Guidance After Output Falls 19% To 400.7 kt In First Quarter
The miner also reported two employee deaths, at Escondida and Peak Downs, and a 53% rise in its realised copper price.
BHP's copper production fell 19% to 400.7 kt in the first quarter of fiscal 2027, from 493.6 kt a year earlier, according to its operational review dated Tuesday and furnished to the SEC on Form 6-K. The company left full-year copper guidance at 1,650 to 1,800 kt.
What the operational review says
The review, for the quarter ended 30 September 2026, also reports that two employees died, one at Escondida and one at Peak Downs. CEO Brandon Craig called them "a profound loss" and said "No loss of life is acceptable." Investigations are underway.
BHP blamed the copper decline mainly on planned lower grades and scheduled maintenance. It added temporary disruptions from severe weather in Chile, stops for safety and the conveyor failure at Carrapateena.
At Escondida, output was 252.6 kt, down 23% from a year earlier. Feed grade was 0.81%, against 0.94%. The fatal incident on 23 September led to a temporary suspension of all mining, and severe weather in July and August constrained logistics and truck use.
The Peak Downs death hit coal, not copper. Operations at all BMA steelmaking coal mines were suspended, for one week at Peak Downs and 24 hours elsewhere. BMA still produced 4.9 Mt, up 1% from a year earlier.
Copper South Australia produced 60.7 kt, down 16%, mostly because of the underground belt failure at Carrapateena. A replacement belt was operational within seven weeks, and the conveyor is now at full capacity.
Prices, guidance and the other commodities
The average realised copper price rose 53% to US$7.01 per pound, from US$4.59. Iron ore fell 9% to US$76.27 per wet tonne, while steelmaking coal rose 34% to US$242.82 per tonne.
Iron ore production rose 4% to 66.5 Mt, with first-quarter records at the WAIO mine and port. Energy coal output rose 26% to 4.4 Mt.
BHP kept every asset-level guidance range it listed, including 1,000 to 1,100 kt for Escondida, 210 to 230 kt for Spence and 290 to 320 kt for Copper South Australia. Spence volumes are weighted to the second half.
At Tuesday's close, BHP shares were at US$81.87, down 1.62% from the prior session.
Growth projects
BHP approved US$0.8 bn (100% basis) of pre-commitment funding for the Escondida New Concentrator. Jansen potash Stage 1 is 87% complete, with first production targeted for mid-2027.
The company aims to lift Copper South Australia output to about 500ktpa by 2035 and up to 650ktpa by 2040. It also announced a larger Olympic Dam mineral resource base.
BHP said it will give more detail on its Copper South Australia strategy at a site visit in November.
Sources
- Form 6-K — Operational review for the quarter ended 30 September 2026 — SEC EDGAR
- BHP: Lower First-Quarter Copper Sales Volume Driven by Escondida, but Better Performance in Iron Ore | Morningstar — morningstar.com
- BHP misses quarterly copper production estimates on Chile mine disruptions (BHP:NYSE) | Seeking Alpha — seekingalpha.com
- BHP Group (ASX:BHP) Keeps Outlook After Copper Drop And Fatal Incident — Yahoo Finance
- BHP to Sell Few Nickel Assets: What's Next for Its Nickel Business? — Yahoo Finance
- La production de cuivre de BHP chute de 19% au premier trimestre — Yahoo Finance