Barrick Removes Nevada Exploration Budget Limits Ahead Of Its Planned North American IPO

Management expects record drilling and spending around North American mines, while Nevada infrastructure improvements lie beyond 2030.

Share
Barrick Removes Nevada Exploration Budget Limits Ahead Of Its Planned North American IPO

Barrick Mining, which produces gold and copper, has removed budget constraints on exploration at Nevada Gold Mines ahead of its planned North American IPO, President and CEO Mark Hill said on the company’s earnings call Monday. The drilling push will help fill gaps in a broader redesign of the mining complex, whose infrastructure improvements management expects after 2030.

More Drilling, A Longer Payoff

“We have unconstrained that budget in NGM,” Hill said, arguing that Nevada Gold Mines remains underexplored. He expects North America to record its busiest year for drilling and exploration spending around existing mines.

The plan reaches beyond Four Mile. Barrick is examining new processing capacity at Cortez and rail infrastructure to move ore across Nevada, with the aim of choosing the best processing route for ore throughout the complex. Hill said rail could lower transport costs across the operations; engineering work on a new roaster is still at an early stage, with a study awarded to Hatch.

Asked by a Jefferies analyst whether the improvements should be expected after 2030, Hill replied: “That's the right way to think about it, yes.”

A Raymond James analyst challenged whether Barrick had enough drilling information to settle the optimization plan. Hill agreed that further work would change the picture, acknowledging “some gaps and things we have to drill off.” He described the current work as a roadmap for identifying what the team needs to investigate.

Four Mile Joins The Bigger Plan

Barrick announced last quarter that it had brought Four Mile under Nevada Gold Mines management. Hill said combining the teams allows the company to consider access to Four Mile through Gold Rush and assess the surrounding infrastructure together.

Exploration between Gold Rush and Four Mile is part of that approach. Management is also advancing drilling along the Gold Rush trend at Cortez and focusing on greater Leeville at Carlin. Barrick is evaluating processing changes that it says could extend open-pit operations beyond 2050.

The spending push comes with cash generation from the operating mines. Barrick produced 816,000 ounces of gold in the third quarter and reported $1.2 billion of consolidated free cash flow. Adjusted earnings per share reached $0.82, up 41% from a year earlier.

North American production was almost half a million ounces. Nevada Gold Mines generated a 67% adjusted margin on earnings before interest, taxes, depreciation and amortization, while Pueblo Viejo generated 72%. Barrick’s market value was $66.8 billion as of 12:11 p.m. ET Monday.

An IPO Against Lower Gold Prices

The planned flotation will meet a different gold market: the metal has fallen about 25% since Barrick confirmed the proposal. The drilling and infrastructure plans form part of the growth case management intends to present to prospective investors.

Barrick’s overall 2026 capital-spending forecast has fallen to $3.8 billion–$4.2 billion, from $4.0 billion–$4.45 billion, chiefly because of reduced spending at Reko Diq. Seb Bock, CEO of Barrick International, said the project remains under active management and review, with feedback to the market expected by the middle of next year.

Hill said Barrick plans to submit its IPO registration statement this month alongside technical reports giving investors a better guide to Nevada Gold Mines and Pueblo Viejo. Management expects the IPO to finish by year-end or early next year, depending on market conditions and regulatory review.

The IPO timetable runs ahead of the Nevada infrastructure payoff: investors will be assessing a drilling-led growth plan whose major processing and rail improvements are expected after 2030.

Sources