Antero Midstream Eyes Several Billion Dollars Of Pipelines, Wants To Be 'The Industrial Builder In West Virginia'

CEO Michael Kennedy expects a final decision on a north-south line in 2027, with over $100 million of added capital planned for next year.

Share
Antero Midstream Eyes Several Billion Dollars Of Pipelines, Wants To Be 'The Industrial Builder In West Virginia'

Antero Midstream, which owns the gathering pipelines and water systems serving gas producers in Appalachia, is pursuing several billion dollars of regional pipeline projects, CEO and President Michael Kennedy said on the company's third-quarter earnings call. He expects a final investment decision on a north-south line toward the Clarington market in 2027.

From gathering to regional pipelines

Kennedy said the company has created a regional pipeline business unit and wants to serve "as the industrial builder in West Virginia." The pipeline list includes its first north-south regional line, laterals to gas demand centers and integrated power opportunities.

He drew a line with earlier waves of Appalachian buildouts: "Unlike the producer push expansions of the past," he said, today's opportunities are driven by demand pull from LNG facilities, utilities and growing electrification. Earlier expansions were farmed out to third parties, he said, while Antero Midstream now has the scale, balance sheet capacity and expertise to pursue the work itself.

As existing third-party agreements expire, the company plans to use its own infrastructure to own more of the value chain those providers served. Antero Resources, the gas producer that is its most significant customer, would see its margins expand under that approach, Kennedy said.

Eastside Express and the north-south line

Since the company announced Eastside Express last quarter, multiple downstream counterparties have shown interest in getting access to Antero Resources' gas through it, Kennedy said. Construction continues.

An analyst at Goldman Sachs asked about the project's scope. CFO Justin Agnew said it is unchanged, with roughly seven interconnects with downstream pipelines and a late 2028 to 2029 timeframe.

On the north-south line, Kennedy said interest in the Clarington market makes building from the company's field a natural, opportunistic move. It is scoping the project with some initial capital, and "you'll probably see us FID that in 2027," he said.

Leverage and 2027 spending

Agnew said adjusted EBITDA was $291 million in the third quarter, up 3% from a year earlier, on $51 million of capital invested. Free cash flow after dividends was $449 million, including $377 million of Clearwater litigation proceeds, and the company cut debt by over $400 million and sped up share repurchases once it hit its leverage target.

Leverage stood at 2.8 times at September 30, below the three-times target. Agnew said 2027 will bring over $100 million of capital beyond the organic program for Eastside Express and other regional gas demand projects. He said that still leaves balance sheet room for larger projects while keeping peer-leading leverage.

Kennedy also said fourth-quarter EBITDA should be an all-time high for the company, with high-single-digit growth from the third quarter, and double-digit EBITDA growth in 2027 over 2026.

The next marker Kennedy named is 2027, when he expects the company to decide on the north-south pipeline.