Albany International Pulls Its Salt Lake City Plant Sale, Booking $11.0 Million Catch-Up Charge

The company put $293.8 million of held-for-sale assets back on its balance sheet after deciding to keep the aerospace composites site.

Share
Albany International Pulls Its Salt Lake City Plant Sale, Booking $11.0 Million Catch-Up Charge

Albany International, which makes paper-machine fabrics and aerospace composite parts, has dropped its plan to sell its Amelia Earhart Drive plant in Salt Lake City, according to its quarterly report filed Thursday. Reversing the sale label cost $11.0 million of catch-up depreciation and amortization in the third quarter.

Why the sale is off

The company said it decided in the third quarter to stop pursuing the sale once its strategic review concluded. Three developments drove the call: new business wins, a renegotiated Boeing 787 contract, and revised CH-53K helicopter terms with Sikorsky, a Lockheed Martin company.

In its prior quarter's filing, Albany had described the process as on schedule, with several expressions of buyer interest and a finish targeted for year-end 2026. The plant had been classified as held for sale since December 31, 2025.

Albany International shares rose 3.41% to $64.60 in Thursday trading, for a market value of $1.8 billion.

$293.8 million back on the books

Reclassifying the plant moved $293.8 million of assets and $203.3 million of liabilities back into regular balance sheet lines. The assets included $68.6 million of contract assets and $21.8 million of goodwill. Depreciation had stopped while the plant was held for sale, so the company resumed it and booked the $11.0 million catch-up for earlier in the year. No impairment loss was recorded because fair value still exceeds carrying value.

Contract assets, net rose to $164.4 million from $87.1 million at year-end. Nine-month operating cash flow fell to $51.6 million from $78.8 million a year earlier, which the company attributed to customer collection timing and inventory growth.

The CH-53K swing

The Salt Lake City site is where staffing and training shortfalls have raised labor and scrap costs on the CH-53 ramp-up, the filing says. In the prior-year nine months, contract adjustments, mainly a loss reserve on CH-53K, were a negative $157.6 million. They were a positive $36.3 million this year after the renegotiation.

Third-quarter gross profit margin was 40.2%, against negative 19.1% a year earlier. Net revenues were $349.5 million. Remaining performance obligations on contracts longer than a year stood at $877.4 million at September 30, mostly firm-fixed-price work at Albany Engineered Composites.

The company has said it will update investors on its path forward at its December investor day, including what the retained Salt Lake City operations mean for Albany Engineered Composites.