Alabama Power Asks To Delay Lindsay Hill Plant Costs Until 2029 To Fit State Rate Freeze
Alabama Power wants regulators to push recovery of a new plant's costs into 2029, while a second petition seeks a liability tied to data-center contracts.
Alabama Power asked state regulators on Wednesday to delay until 2029 the recovery of costs for its Lindsay Hill Generating Station, Southern Company said in its quarterly report on Thursday. The request is meant to square the plant's already-approved cost recovery with what the filing calls the "apparent intent" of Alabama's new rate-freeze law.
How the deferral would work
Alabama Power filed the request on November 4 alongside a Rate CNP New Plant filing, the mechanism through which regulators had previously approved recovery of the Lindsay Hill costs. During 2028, retail customers would get credits that neutralize the rate effect of that recovery, which begins in January 2028.
The utility would also set up a regulatory asset for the costs in 2028 and recover it over five years starting in 2029. The filing says the outcome "cannot be determined at this time."
The trigger is the Power to the People Act, enacted April 2, 2026. It bars increases to retail base rates in place on October 1, 2026 before January 1, 2029. The law followed a December 2025 consent order from the Alabama Public Service Commission that held retail rates stable through 2027.
A new liability for data-center contracts
A separate October 16 petition asks the commission to authorize, effective October 1, 2026, a liability for future Potential Cost Exposure. That is the risk tied to expected incremental investment to serve certain customers.
The petition aligns the liability with an Incremental Revenue Component that Alabama Power has written into certain electric service contracts, on top of pricing, early termination fees and guarantees or surety bonds. As those revenue amounts are billed, the utility would record a matching liability, then start drawing it down once risk-mitigation thresholds are met. The language is new compared with the prior quarter's filing.
Georgia's $949 million pledge
Southern Company is a holding company that owns Alabama Power, Georgia Power, Mississippi Power, Southern Power and Southern Company Gas.
In Georgia, after signing additional large-load contracts, Georgia Power agreed on August 26 to put at least $949 million a year of downward pressure on rates for customers outside the large-load group in its next base rate case, on a levelized basis, for 2029, 2030 and 2031. It also agreed not to seek recovery from those customers for revenue shortfalls if a data-center customer ends a contract early, though the Georgia commission keeps discretion to allow such recovery.
The commission is expected to decide on December 15, 2026 a proceeding on how revenue from variable demand-driven pricing customers is assigned to fuel cost recovery.
Both Alabama requests await a ruling from the Alabama commission; the Georgia pricing decision is expected December 15, 2026.
Sources
- 10-Q Filing — Southern Company (SO) — SEC EDGAR
- 10-Q Filing — Southern Company (SO), Q2 FY2026 filed 2026-07-30 (comparison basis) — SEC EDGAR
- Curious about Southern Co. (SO) Q3 Performance? Explore Wall Street Estimates for Key Metrics — Yahoo Finance
- Did Bylaw Changes Just Shift Southern's (SO) Investment Narrative? — Yahoo Finance
- How Will Southern Stock React To Its Upcoming Earnings? — Yahoo Finance
- Southern Co Q3 2026 earnings preview: Analysts see case for results growth (NYSE:SO) | Seeking Alpha — seekingalpha.com
- 4 Utility Stocks Set to Outperform Q3 Earnings Estimates This Season — Yahoo Finance