# Kinder Morgan's Project Backlog Jumps To $14.4 Billion From $9.6 Billion After Two Pipeline Approvals
- URL: https://www.bullished.co/kinder-morgans-project-backlog-jumps-to-14-4-billion-from-9-6-billion-after-two-pipeline-855abf8e/
- Published: 2026-10-21T22:06:03.000Z
- Updated: 2026-10-29T19:26:17.000Z
- Description: President Kim Dang said $5.4 billion of additions and $700 million of in-service projects moved the backlog, with capital spending near $4 billion a year.
- Author: Matteo Parrino
- Tags: Earnings, KMI, Industry: Energy

[Kinder Morgan](https://www.bullished.co/tag/kmi/)'s project backlog rose to $14.4 billion from [$9.6 billion](https://finance.yahoo.com/markets/stocks/articles/why-did-kinder-morgan-kmi-221403545.html?ref=bullished.co), President Kim Dang said on the company's third-quarter earnings call. She said $5.4 billion of new projects were added and $700 million of projects were placed into service.

## Two joint-venture pipelines drive the additions

Dang said the company's share of the two new joint ventures, SNG's Southeast Connector and NGPL's Permian Link, is about $4.7 billion. Both carry take-or-pay contracts of at least 20 years, meaning shippers pay for capacity whether or not they use it.

Southeast Connector is contracted with strong investment-grade utilities. Permian Link is contracted with an A-rated hyperscaler, a large cloud and data-center operator. Dang said the backlog multiple is 5.7 times, which she called very attractive.

SouthEast Connector is designed to deliver about 2.6 BCF a day (billion cubic feet of gas) into the region. Dang said Permian Link comes online in 2030, while Southeast Connector comes on in 2030, 2031 and 2032\. Before this quarter, she said, most of the backlog's EBITDA was expected online by the end of 2029.

Sital Nagaraj, senior vice president of commercial, told a Barclays analyst that scaling Southeast Connector to 3.5 BCF a day is plausible. The project is in a binding open season, and he said the final size depends on who signs. Dang said signed commitments already support a final investment decision.

## Spending, returns and the shadow backlog

Dang said capital spending should run around $4 billion a year for the next few years. She said the company ended the quarter at about 3.5 times debt to EBITDA, with roughly $3 billion of annual cash flow available for expansion.

Executive Chairman Rich Kinder said the returns on the $14.4 billion backlog equal $2.5 billion of additional EBITDA, which he said pushes the company to between $11.5 billion and $12 billion.

A Wells Fargo analyst said the roughly $1.5 billion capital estimate for the TGP 219 South expansion was lower than the firm had expected. Nagaraj, who gave that figure, said a build of 2 to 3 BCF a day would cost more, and that the company is focused on the brownfield portion, meaning expansion of existing infrastructure.

On the earlier "shadow backlog" of more than $10 billion in unsigned opportunities, Dang said a substantial amount remains. She said new projects will create bottlenecks elsewhere that lead to more work, and she hopes the $14.4 billion has established credibility.

## Kinder's closing message

Kinder said that on the prior call there was some skepticism about whether the company could bring its projects along. He said he had remarked then that the company had to get the horses in the corral.

His closing line: "we've got a hell of a lot of those horses in the corral now with the saddles on. But we've got more horses just outside the corral."

The Southeast Connector open season is still running, and Nagaraj said the project's final size depends on who signs.

Learn

- [How To Read An Earnings Call Transcript: Start With Guidance, Then Find What's Missing →](https://www.bullished.co/learn/how-to-read-an-earnings-call/)  
How to read an earnings call transcript: check guidance first, look for dropped metrics, compare growth with last quarter, and watch hedged wording.

### Sources

- [Why Did Kinder Morgan (KMI) Shares Climb Ahead Of Its Latest Update?](https://finance.yahoo.com/markets/stocks/articles/why-did-kinder-morgan-kmi-221403545.html?ref=bullished.co) — Yahoo Finance
- [Wall Street's Insights Into Key Metrics Ahead of Kinder Morgan (KMI) Q3 Earnings](https://finance.yahoo.com/markets/stocks/articles/wall-streets-insights-key-metrics-121507334.html?ref=bullished.co) — Yahoo Finance
- [Kinder Morgan’s (NYSE:KMI) Q3 2026: strong sales](https://finance.yahoo.com/energy/articles/kinder-morgan-nyse-kmi-q3-201849658.html?ref=bullished.co) — Yahoo Finance
- [Kinder Morgan Q3 earnings preview: EPS growth of 13.8%, revenue expected to rise 5.7% (KMI:NYSE) | Seeking Alpha](https://seekingalpha.com/news/4655190-kinder-morgan-q3-earnings-eps-growth-of-138-revenue-expected-to-rise-57?ref=bullished.co) — seekingalpha.com
- [Is Kinder Morgan (KMI) a Good or Bad Investment at This Price?](https://finance.yahoo.com/markets/stocks/articles/kinder-morgan-kmi-good-bad-170321592.html?ref=bullished.co) — Yahoo Finance

### More on Kinder Morgan

- [Kinder Morgan Books $138 Million Legal Charge As Its Reserve For Such Matters Hits $397 Million](https://www.bullished.co/kinder-morgan-books-138-million-legal-charge-as-its-reserve-for-such-matters-hits-397-af53069e/)
- [Kinder Morgan's Gas Project Backlog Hits $13.2 Billion, Largest In Its History, As Quarterly Profit Sets Record](https://www.bullished.co/kinder-morgans-gas-project-backlog-hits-13-2-billion-largest-in-its-history-as-quarterly-1a9536d8/)

[All Kinder Morgan (KMI) coverage →](https://www.bullished.co/tag/kmi/)