# Google Agrees To Backstop Anthropic's Rent On TeraWulf's Kentucky Campus, A $19 Billion Lease Package
- URL: https://www.bullished.co/google-agrees-to-backstop-anthropics-rent-on-terawulfs-kentucky-campus-a-19-billion-lease-018913c8/
- Published: 2026-11-04T13:26:07.000Z
- Updated: 2026-11-04T13:26:07.000Z
- Description: TeraWulf also signed a definitive Fluor construction deal, with phased service beginning in late 2027.
- Author: Matteo Parrino
- Tags: SEC Filings, WULF, Industry: Technology

Google agreed Wednesday to cover certain rent obligations of Anthropic at TeraWulf's Hawesville, Kentucky data center campus, under [three credit support agreements](https://www.sec.gov/Archives/edgar/data/0001083301/000162828026069810/wulf-20261104.htm?ref=bullished.co) tied to about $19 billion of lease commitments, [TeraWulf](https://www.bullished.co/tag/wulf/) said in an [8-K](https://www.bullished.co/learn/8-k-items-explained/). The data center developer also announced a definitive construction contract with Fluor.

## How the Google backstop works

TeraWulf owns and develops data center campuses built for high-performance computing and AI workloads, and leases the capacity to large cloud and enterprise customers. Its subsidiary Raylan Data signed a 20-year lease with Anthropic in July 2026 for about 401 MW of critical IT load at the Kentucky campus, across three data halls.

The three agreements, one for each hall, were signed Wednesday with Google, Anthropic, Raylan and a TeraWulf subsidiary. If Anthropic defaults on rent or becomes insolvent, Google can pay the rent due and take over as tenant. In certain circumstances it can instead pay a termination fee, and that payment would entitle it to an equity interest in Raylan.

In a default, Google may also put off that choice for a set period, paying all unpaid and newly due rent in the meantime. The termination fee shrinks over a defined term after the backstop takes effect.

The backstop becomes effective when the final data hall under each lease begins. It ends on conditions that include Anthropic, or an affiliate guaranteeing its lease, reaching and keeping certain investment-grade credit ratings for at least three months.

## Financing and the Fluor contract

The support is meant to help TeraWulf line up debt for the project. Google is a subsidiary of Alphabet, whose senior unsecured debt is rated AA+ by S&P Global Ratings and Aa2 by Moody's, the company said in its press release. CFO Patrick Fleury said strong investment-grade support improves the project's financing profile and its ability to pursue competitive long-term debt.

The Fluor agreement covers engineering, procurement and construction of three data center buildings. It builds on a limited notice to proceed announced in March 2026 and widens Fluor's role to include construction, testing and commissioning. It sets delivery milestones, open-book cost reporting and procurement oversight.

Guaranteed maximum pricing is still being set as engineering and procurement advance. Ready-for-service completions are expected to start in late 2027 and run through the second quarter of 2028, matching the lease delivery schedule.

## Where Kentucky fits in the portfolio

Chairman and CEO Paul Prager said Fluor lets TeraWulf "scale execution without building a global engineering and construction organization internally." He also said "megawatts alone do not create shareholder value."

The company runs the Lake Mariner campus in New York, where it also operates bitcoin mining. It recently expanded contracted power capacity to 1 GW at its Muskie Data Campus in eastern Kentucky.

The debt financing the Google backstop is meant to support is still anticipated, and Fluor's guaranteed maximum pricing is still being established.

Learn

- [Item 1.01: entry into a material agreement →](https://www.bullished.co/learn/8-k-items-explained/#item-101-entry-into-a-material-agreement)  
From 8-K Items Explained: What Every Item Code From 1.01 To 9.01 Tells You, With Examples

### Sources

- [8-K Filing — TERAWULF INC. (WULF)](https://www.sec.gov/Archives/edgar/data/0001083301/000162828026069810/wulf-20261104.htm?ref=bullished.co) — SEC EDGAR
- [Exhibit wulfhawesvillecsaandepcmpr.htm — TERAWULF INC. 8-K exhibit](https://www.sec.gov/Archives/edgar/data/0001083301/000162828026069810/wulfhawesvillecsaandepcmpr.htm?ref=bullished.co) — SEC EDGAR

### More on TeraWulf

- [TeraWulf Expands Its Revolving Credit Line To About $400 Million From $250 Million](https://www.bullished.co/terawulf-expands-its-revolving-credit-line-to-about-400-million-from-250-million-1950167e/)
- [TeraWulf Doubles Muskie Power Contract To 1 Gigawatt And Moves Phase Two Up A Year](https://www.bullished.co/terawulf-doubles-muskie-power-contract-to-1-gigawatt-and-moves-phase-two-up-a-year-cd293409/)

[All TeraWulf (WULF) coverage →](https://www.bullished.co/tag/wulf/)